Natural Gas Pipeline Permitting Reform Act
Official title: To provide for the timely consideration of all licenses, permits, and approvals required under Federal law with respect to the siting, construction, expansion,… Show full official titleShow less
Official title: To provide for the timely consideration of all licenses, permits, and approvals required under Federal law with respect to the siting, construction, expansion, or operation of any natural gas pipeline projects.
More subjectsShow fewer subjects
| Date | Chamber | What was voted on | Result | Yes–No | |
|---|---|---|---|---|---|
| Nov 21, 2013 | House · vote #611 | On Passage | Passed | 252–165 | See who voted → |
| Nov 21, 2013 | House · vote #610 | On Motion to Recommit with Instructions | Failed | 180–233 | See who voted → |
Amendments propose changes to this bill. Members vote on amendments separately before the final bill vote. An agreed amendment becomes part of the bill; a failed amendment does not.
5 failed 1 pending / other
| Amendment | Sponsor | Status |
|---|---|---|
| HAMDT 516 | – | Failed |
| HAMDT 515 | – | Failed |
| HAMDT 514 | – | Failed |
| HAMDT 513 | Castor, Kathy | Failed |
| HAMDT 512 | Tonko, Paul | Failed |
| HAMDT 517 | – | Pending |
Have a question about what this bill does? Ask in plain English; the answer is drawn from the bill's actual text and official record, and it'll tell you when something isn't in the text rather than guess.
Received in the Senate and Read twice and referred to the Committee on Commerce, Science, and Transportation.
(This measure has not been amended since it was reported to the House on November 18, 2013. The summary of that version is repeated here.)
Natural Gas Pipeline Permitting Reform Act - Amends the Natural Gas Act to direct the Federal Energy Regulatory Commission (FERC) to approve or deny a certificate of public convenience and necessity for a prefiled project within 12 months after receiving a complete application that is ready to be processed.
Defines "prefiled project" as a project for the siting, construction, expansion, or operation of a natural gas pipeline with respect to which a prefiling docket number has been assigned by FERC pursuant to a prefiling process established by FERC for the purpose of facilitating the formal application process for obtaining a certificate of public convenience and necessity.
Requires the agency responsible for issuing any federal license, permit, or approval regarding the siting, construction, expansion, or operation of a project for which a certificate is sought to approve or deny issuance of the certificate within 90 days after FERC issues its final environmental document regarding the project.
Requires FERC to grant an agency request for a 30-day extension of the 90-day time period if the agency demonstrates that it cannot otherwise complete the process required to approve or deny the license, permit, or approval, and therefore will be compelled to deny it.
Authorizes FERC, in granting such an extension, to offer technical assistance to the agency in order to address conditions preventing completion of the application review.
Declares that, if the agency fails to approve or deny issuance of a permit, license, or approval within the prescribed time-frame, the license, permit, or approval shall take effect upon expiration of 30 days after the period's end.
Directs FERC to incorporate into the terms of a license, permit, or approval any conditions proffered by the agency that FERC does not find to be inconsistent with the final environmental document.
- Engrossed in House Formatted Text PDF Formatted XML
- Introduced in House Formatted Text PDF Formatted XML
- Referred in Senate Formatted Text PDF Formatted XML
- Reported in House Formatted Text PDF Formatted XML
Cite this page
U.S. Congress. (2026). H.R. 1900: Natural Gas Pipeline Permitting Reform Act. 113th Congress. Open America. https://openamerica.io/bill/113-HR-1900/
"H.R. 1900: Natural Gas Pipeline Permitting Reform Act." 113th Congress, 2026, Open America, https://openamerica.io/bill/113-HR-1900/.
H.R. 1900, 113th Cong. (2026), https://openamerica.io/bill/113-HR-1900/.
[H.R. 1900: Natural Gas Pipeline Permitting Reform Act](https://openamerica.io/bill/113-HR-1900/)