Skip to main content
S 2652 113th Congress Senate Government Operations and Politics Building construction Congressional oversight Government buildings, facilities, and property Government studies and investigations Military procurement, research, weapons development Public contracts and procurement

A bill to improve the design-build process in Federal contracting.

Introduced: July 24, 2014 Introduced by: Fischer, Deb Republican · Nebraska See on congress.gov
This bill died when the 113th Congress ended
It never became law before the 113th Congress (2013–2014) adjourned, and bills don't carry over to the next Congress. It would have to be reintroduced. You can still save it for reference, but it won't receive updates.
 Everywhere this bill has been 2 steps
Introduced
In committee
Reported out
Passed House
Passed Senate
To President
Became law
Jul 24, 2014
Read twice and referred to the Committee on Homeland Security and Governmental Affairs.
Jul 24, 2014
Introduced in Senate
 Ask about this bill AI · grounded in the bill text

Have a question about what this bill does? Ask in plain English; the answer is drawn from the bill's actual text and official record, and it'll tell you when something isn't in the text rather than guess.

AI answers can be imperfect; always confirm against the full bill text.

 Plain-English summary Congressional Research Service

Modifies design-build selection procedures for civilian and defense contracts for the design and construction of a public building, facility, or work to require the contracting officer to provide written documentation of how more than five finalists in a solicitation for a contract is consistent with the purposes and objectives of the two-phase selection process (a procurement process in which the first phase consists of prequalification or shortlisting and the second phase consists of preparation and submission of complete design-build proposals from the prequalified offerors).

Requires the use of two-phase selection procedures for civilian or defense contracts when a contracting officer determines that the contract has a value of $750,000 or greater, adjusted for inflation. Requires: (1) agencies to report on contracts for which more than five finalists were selected for phase-two requests or for which the contract was awarded without using two-phase selection procedures, and (2) the Comptroller General (GAO) to report on the compliance of executive agencies with design-build contract procedures.

What's happening now July 24, 2014

Read twice and referred to the Committee on Homeland Security and Governmental Affairs.

 Related & companion bills 1
 Bill text 1 version

Source documents hosted by congress.gov.

 Committees of jurisdiction 1
Cite this page click to expand
APA
U.S. Congress. (2026). S. 2652: A bill to improve the design-build process in Federal contracting.. 113th Congress. Open America. https://openamerica.io/bill/113-S-2652/
MLA
"S. 2652: A bill to improve the design-build process in Federal contracting.." 113th Congress, 2026, Open America, https://openamerica.io/bill/113-S-2652/.
Bluebook (legal)
S. 2652, 113th Cong. (2026), https://openamerica.io/bill/113-S-2652/.
Markdown link
[S. 2652: A bill to improve the design-build process in Federal contracting.](https://openamerica.io/bill/113-S-2652/)