Hoover Power Allocation Act of 2010

Introduced: December 16, 2009 See on congress.gov
 Everywhere this bill has been 19 steps
Introduced
In committee
Reported out
Passed House
Passed Senate
To President
Became law
Sep 27, 2010
Committee on Energy and Natural Resources. Reported by Senator Bingaman without amendment. With written report No. 111-329.
Sep 27, 2010
Placed on Senate Legislative Calendar under General Orders. Calendar No. 615.
Jul 21, 2010
Committee on Energy and Natural Resources. Ordered to be reported without amendment favorably.
Jun 9, 2010
Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.
Jun 8, 2010
Passed/agreed to in House: On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote.(text: CR H4219-4221)
Jun 8, 2010
Considered under suspension of the rules. (consideration: CR H4219-4222)
Jun 8, 2010
Mrs. Napolitano moved to suspend the rules and pass the bill, as amended.
Jun 8, 2010
DEBATE - The House proceeded with forty minutes of debate on H.R. 4349.
Jun 8, 2010
Motion to reconsider laid on the table Agreed to without objection.
Jun 8, 2010
On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote. (text: CR H4219-4221)
May 28, 2010
Placed on the Union Calendar, Calendar No. 287.
May 28, 2010
Reported (Amended) by the Committee on Natural Resources. H. Rept. 111-502.
May 5, 2010
Ordered to be Reported (Amended) by Voice Vote.
May 5, 2010
Committee Consideration and Mark-up Session Held.
May 5, 2010
Subcommittee on Water and Power Discharged.
Mar 18, 2010
Subcommittee Hearings Held.
Jan 4, 2010
Referred to the Subcommittee on Water and Power.
Dec 16, 2009
Referred to the House Committee on Natural Resources.
Dec 16, 2009
Introduced in House
 Plain-English summary Congressional Research Service

(This measure has not been amended since it was passed by the House on June 8, 2010. The summary of that version is repeated here.)

Hoover Power Allocation Act of 2010 - (Sec. 2) Amends the Hoover Power Plant Act of 1984 (HPPA) to modify, commencing October 1, 2017, certain statutory schedules governing contracts for delivery of hydroelectric power generated at Hoover Dam to specified localities in Arizona, California, and Nevada.

Directs the Secretary of Energy to: (1) create, from certain apportioned allocations of contingent capacity and firm energy, a resource pool equal to 5% of the full rated capacity of 2.074 million kilowatts and associated firm energy; (2) offer Schedule D contingency capacity and firm energy to new allottees not receiving contingent capacity and firm energy for delivery commencing October 1, 2017; and (3) allocate through the Western Area Power Administration (WAPA) for delivery commencing October 1, 2017, 66.7% of Schedule D contingent capacity and firm energy to specified new allottees within the marketing area for the Boulder City Area Projects.

Requires, in the case of Arizona and Nevada, Schedule D contingent capacity and firm energy for new allottees other than federally recognized Indian tribes to be offered through the Arizona Power Authority and the Colorado River Commission of Nevada, respectively. Requires Schedule D contingent capacity and firm energy that is allocated to federally recognized Indian tribes to be contracted for directly with WAPA.

Grants WAPA 36 months to complete allocation to new allottees in California.

Requires each contract offered under HPPA to: (1) authorize and require WAPA to collect from new allottees a pro rata share of Hoover Dam repayable advances paid for by contractors before October 1, 2017, and to remit such amounts to the contractors that paid such advances in proportion to the amounts paid by them as specified in a certain Implementation Agreement; (2) permit transactions with an independent system operator; and (3) contain the same material terms included in those long-term contracts for purchases from the Hoover Power Plant that were made in accordance with HPPA and are in existence on the date of enactment of this Act.

Subjects the contractual obligation of the Secretary to deliver contingent capacity and firm energy under HPPA to the availability of the water needed to produce such contingent capacity and firm energy.

Continues through FY2067 the requirements of HPPA as the exclusive method for the disposal of capacity and energy from Hoover Dam (in effect, congressional oversight).

(Sec. 3) Requires the budgetary effects of this Act, for the purpose of complying with the Statutory Pay-As-You-Go Act of 2010, to be determined by reference to the latest statement titled "Budgetary Effects of PAYGO Legislation" for this Act, submitted for printing in the Congressional Record by the Chairman of the House Budget Committee, provided that such statement has been submitted prior to the vote on passage.

What's happening now September 27, 2010

Placed on Senate Legislative Calendar under General Orders. Calendar No. 615.

 Committees of jurisdiction 3